HVAC tenant improvement scope of work

How to write the mechanical scope for a commercial tenant improvement: duct and VAV changes, zoning, landlord approval, base-building limits and hours.

For tenants, tenant representatives, general contractors, property managers. 5 min read. Updated November 2026.

Short answer

A tenant improvement HVAC scope should state which work is tenant-side and which belongs to the base building, what the landlord must approve before work starts, and when work is allowed. It should list duct, diffuser, VAV box, zoning and thermostat changes by location, name who handles electrical, ceilings and permits, and define after-hours access, so the bid matches what the building will actually permit.

Key points
  • A TI scope starts with a boundary: what is the tenant's mechanical system, and what is the landlord's base-building system you are only connecting to.
  • Landlord approval is a scope item. Plans, equipment changes and work on shared systems usually need written sign-off before ordering anything.
  • VAV box adds and relocations are only as good as the air available upstream. The scope should say who confirms supply capacity.
  • Thermostat and zone changes need a defined point of control, otherwise a new zone gets built that nobody can adjust.
  • After-hours work is normal in occupied buildings. The scope should name hours, access, freight and noise rules rather than leave them for later.

Draw the line between tenant work and base building

Almost every TI dispute traces back to one question: whose system is it? In a leased suite, the landlord typically owns the central plant, main risers, rooftop equipment serving the floor and the primary supply duct. The tenant's work usually starts at a connection point downstream of that, but leases differ, so the scope should not guess.

Put the boundary in writing, floor by floor if needed. A one-line statement such as "work begins at the base-building branch connection shown on sheet M-2" removes a large category of argument later. If the lease or work letter defines the split, reference it by name in the scope.

Typical split of responsibility (confirm against the lease and work letter)
ItemUsually tenant scopeUsually base-building scope
Branch ductwork and diffusers inside the suiteYesNo
Main supply and return trunks, risersConnect to onlyYes
VAV boxes serving the suiteOften yes when added or movedSometimes owned by landlord even inside the suite
Rooftop or central equipmentOnly if the TI adds a dedicated unitYes
Controls tied to the building systemSuite-level devicesHead-end, graphics, network
Fire dampers, smoke detection interfaceCoordinateOften landlord-controlled

What the mechanical scope should list

A good TI scope reads like a marked-up floor plan in words. Each item has a location, an action and a result. Vague lines such as "modify ductwork as needed" are where change orders come from. See how to write a commercial HVAC scope of work for the general structure.

  • Demolition of existing branch duct, diffusers and controls in the affected area, with a note on what is reused versus discarded.
  • New or relocated branch duct, flex runs, diffusers and returns, by room or zone.
  • VAV boxes added, relocated or reheated, with the reheat type stated.
  • New thermostats or sensors, with mounting height and location coordinated to the architectural plan.
  • Connection to the base-building control system, if one exists, and who programs it.
  • Air balancing of the altered zones and who performs it.
  • Permit, inspection and closeout items that belong to the mechanical trade.

Duct and diffuser changes

Ceiling grid and layout

Diffusers sit in a ceiling the ceiling contractor and lighting contractor are also working in. The scope should say who sets the grid openings and who supplies the ceiling tile cut. Mechanical typically supplies and connects the diffuser, but a flat statement removes doubt.

Reuse of existing duct

Reusing old duct saves material but carries risk. Existing flex may be sagging, torn or insulated with deteriorated wrap. If reuse is assumed, the scope should say whether the contractor inspects it, cleans it or accepts it as found. Add a line on how hidden conditions above the ceiling are handled, since they are a classic trigger for HVAC change orders.

Return air path

New walls that reach the deck can strangle a return. If the plan adds a full-height partition, the scope should require a transfer duct, a return grille or a plenum path, and name it.

VAV boxes, zoning and thermostat changes

Adding a VAV box is rarely just hanging a box. It adds airflow demand to a trunk that was sized for the old layout. The scope should state whether the contractor is responsible for verifying available supply air, or whether the design engineer provides the airflow schedule and the contractor installs to it.

  1. Confirm the airflow schedule for each new or relocated box, and who issued it.
  2. State the box type, inlet size, reheat and control sequence expected.
  3. Identify the controller and who supplies and programs it.
  4. Define upstream work: duct resizing, balancing dampers, static pressure reset.
  5. Define the thermostat or sensor served by each box and where it mounts.

Zoning changes deserve their own line. Combining three offices on one thermostat is a design decision, and splitting a conference room onto its own zone is another. The scope should record which zones exist after the work, so occupants have a way to ask for adjustments. Controls tied to the base building are covered in more depth in building automation controls upgrade scope of work.

Landlord approval and coordination sequence

Treat approval as a sequence the schedule depends on. Order equipment only after the steps that gate it are done.

  1. Submit mechanical drawings and equipment data to the landlord or property manager for review.
  2. Receive written approval, including any conditions on riser access, roof access or shutdown windows.
  3. Confirm insurance certificates and any contractor registration the building requires.
  4. Schedule shutdowns or tie-ins to base-building systems with building engineering.
  5. Confirm permit status with the authority having jurisdiction before starting concealed work.
  6. After completion, deliver as-built markups and balance reports to the landlord if the lease requires them.
Who does the non-mechanical work

A TI mechanical scope touches electrical service to new boxes, ceiling patching, fire-life-safety interfaces and structural support. Davinci's mechanical, refrigeration and controls work is performed by its own UA Local 250 crew. The scope should name who performs electrical, ceiling and any structural work, and the owner or general contractor should confirm the responsible licensed party for each.

After-hours work and occupied-building constraints

Office towers and medical suites often restrict noisy work, shutdowns and freight use to nights or weekends. If the work is after hours, say so in the scope and define what that means in your building: allowed hours, freight elevator reservation, loading dock access, security escort and whether the building charges for after-hours HVAC.

  • Hours of permitted work and any blackout days such as month-end or tenant events.
  • Dust, noise and odor controls near neighboring tenants.
  • Protection of finished corridors, lobbies and elevators.
  • Temporary cooling or heating if a zone is down during occupied hours.
  • Refrigerant, solvent or brazing restrictions if the building prohibits hot work near occupants.

Phasing in occupied space is a larger topic; the same logic is covered in phasing an HVAC conversion in an occupied office.

Sample scope language

Contractor shall furnish and install branch duct, diffusers, returns and VAV boxes in the areas shown on the mechanical drawings, beginning at the base-building connection points identified by Owner. Work requiring shutdown of base-building systems or use of freight elevators shall be performed during the hours approved in writing by building management. Contractor shall not order equipment until Owner confirms landlord approval of submittals. Electrical service, ceiling work and fire-life-safety modifications are excluded unless listed.

Frequently asked questions

Who pays for HVAC changes in a tenant improvement?
That depends on the lease and the work letter, not on the contractor. Some landlords provide an allowance and own certain base-building items, while the tenant pays for the rest. The scope should simply label each line item as tenant or landlord scope so the right party reviews and approves it.
Do I need landlord approval to move a thermostat or diffuser?
Often yes when the change touches a shared or base-building system, and sometimes even for suite-only work under the lease. Confirm the requirements in writing before ordering equipment. Approval can include drawings, equipment data, insurance and an agreed work schedule. Asking early costs little, and starting without it can mean stopped work or removal of what was installed.
Can existing duct be reused in a TI?
Sometimes. Reuse depends on condition, size and the new airflow needs. The scope should state whether the contractor inspects and cleans reused duct or accepts it as found, and how hidden defects are handled if they turn up above the ceiling. A short ceiling-cavity inspection during the site walk is cheap insurance.
Who balances the air after a TI?
The scope must name the party. It may be the mechanical contractor, an independent agency hired by the owner, or an agency the landlord requires. Do not assume it is included. See the testing, balancing and commissioning scope for how to define it. Also decide who pays if zones must be rebalanced after the ceiling work changes.
Why does after-hours work change the scope?
It changes access, labor scheduling, freight use, noise limits and sometimes building HVAC charges. If the work must happen at night or on weekends, say so when the bid is requested so every bidder prices the same conditions. Late discovery of a night-only restriction is one of the most common reasons a TI bid comes back with changes.

Performed by our own crew. No subcontractors.

The mechanical, refrigeration and controls work on our projects is done by our own UA Local 250 workforce. The people who price the job are the people who set the equipment, pipe it, charge it and start it up, so one team answers for every task in the scope. Rented equipment such as a crane truck is coordinated by us.

How self-performed work works

Send us the scope or the drawings.

If you are pricing a project or reviewing a bid, send the plans, the spec section or the equipment list. We will tell you what we would clarify before pricing it. Davinci Mechanical is the commercial and union division of Scottish Tom's Heating & Air.