Testing, balancing and commissioning scope of work

What testing and balancing, startup and commissioning each include, how to name the responsible party, and how functional and seasonal tests are documented.

For owners, design teams, general contractors, facility managers. 4 min read. Updated November 2026.

Short answer

Testing and balancing measures and adjusts airflow and water flow to design values. Commissioning verifies that systems work together as intended, using functional performance tests. Equipment startup and checkout is a third, separate activity performed by the installing contractor. Independent agencies often perform TAB and commissioning, so the scope must name who does each and what deliverables are required.

Key points
  • Startup, test and balance, and commissioning are three different activities. A scope that blurs them leaves gaps nobody notices until occupancy.
  • Independent TAB and commissioning agencies are common. Name the agency, who hires it and who pays for retesting.
  • Davinci performs startup and checkout of the equipment it installs. That is not the same as third-party TAB or an owner's commissioning agent.
  • Functional performance tests need written sequences to test against. Seasonal testing may be needed when conditions during construction cannot exercise a system.
  • The deliverable is documentation: reports, deficiency lists, resolution records and final sign-off.

Three activities that get mixed up

On many projects the same phrase, "test and balance," gets used to cover work that belongs to three different parties. Separating them in the scope is the simplest way to prevent a gap or a double charge.

ActivityWhat it isTypically performed by
Startup and checkoutEnergizing and verifying that installed equipment starts, runs safely and meets basic operating parametersThe installing contractor, with manufacturer support where required
Testing and balancing (TAB)Measuring and adjusting airflow and water flow, recording results against designAn independent TAB agency or a qualified party named in the contract
Commissioning (Cx)Verifying systems meet the owner's project requirements through documented review and functional testingAn owner-selected commissioning agent or a designated team

Davinci's mechanical, refrigeration and controls crew does the startup and checkout of the equipment Davinci installs. Test and balance by a third-party agency, and owner-side commissioning, are separate roles that the owner or general contractor must assign and confirm.

Name the party, the hiring chain and the access rules

A common failure is a scope that says "system shall be balanced" without saying who balances it. Fix it with four answers.

  1. Who performs the work: agency name or the qualification the owner requires.
  2. Who hires and pays the agency: owner, general contractor or mechanical contractor.
  3. What the mechanical contractor must provide: accessible equipment, open dampers, clean filters, set belts, working controls and a ready-for-balancing notice.
  4. Who pays for repeated visits when the system was not actually ready.

Specifications on public projects often require certification of the agency by a recognized body. Confirm the requirement in the documents. For bid-package reading, see public works HVAC bid scope.

Startup and checkout: what the installing contractor owns

Startup is the contractor's proof that the equipment works as installed. It comes before balancing, because an agency cannot measure a system that is not running correctly.

  • Electrical readiness confirmed with the responsible party: voltage, phase and disconnects.
  • Rotation, belt tension, alignment and lubrication checks on fans and motors.
  • Refrigerant circuit checks: charge, pressures, superheat and subcooling readings recorded.
  • Safety devices verified, including pressure cutouts, freeze protection and limit switches.
  • Gas train and combustion checks where applicable, and condensate and drain testing.
  • Controls point-to-point verification and confirmation that the sequence runs.
  • Startup report with serial numbers, readings and photos.

Those records become the baseline for future maintenance. When the startup readings sit in an asset record such as the DaVinci Portal, later readings have something to be compared against.

What a TAB scope should require

A balancing agency measures supply, return and exhaust airflow at terminals and equipment, adjusts dampers, pulleys and drives, and reports results against design. On hydronic systems the same applies to pump and coil flow. The scope should state the standard of acceptance, such as a tolerance to design values, that the contract defines.

Report content

  • Instrument list and calibration status.
  • Design versus measured values by terminal, coil and equipment.
  • Final damper, valve and drive settings.
  • Deficiencies noted, with who is responsible for correction.
  • Drawings or schedules marked with measured values.

Balancing is sensitive to later changes. After a tenant improvement or a controls upgrade, rebalance the affected zones and update the report.

Functional performance tests and seasonal testing

Functional performance tests (FPTs) force a system through its sequence and record what actually happens. They need a written sequence of operation, which is why an unclear sequence is a commissioning problem as well as a programming one. See building automation controls upgrade scope.

  1. Commissioning agent writes test procedures from the approved sequences.
  2. The mechanical and controls contractors prepare the system and confirm readiness.
  3. Tests run, with results recorded: pass, fail or not testable.
  4. Deficiencies are listed, corrected by the responsible party and retested.
  5. Final report shows resolution of each item and any open issues.

Seasonal testing matters because a building finished in a mild month cannot prove it handles peak cooling or winter heating. If the scope calls for deferred tests, state which ones, when they occur, who attends and how results are added to the record. Heating tests in a building commissioned during summer, and peak-cooling tests during a cooler season, are typical examples. Economizer and energy-code acceptance items should be confirmed against current Title 24 requirements.

Documentation that closes the job

The finish line for this scope is paper that the owner can use later. Without it, the building has equipment that works today and no proof of how it was set up.

  • Startup reports from the installing contractor.
  • Final TAB report, signed by the responsible agency.
  • Commissioning plan, test procedures, completed FPTs and issues log.
  • Updated sequences of operation and controls backups.
  • Training records for operators and maintenance staff.
  • Seasonal test schedule and results when deferred tests are required.
Sample scope language

Contractor shall perform startup and checkout of the equipment it installs and shall deliver startup reports to Owner. Testing and balancing shall be performed by the independent agency named in the contract documents, and Contractor shall provide a written notice when systems are ready for balancing. Contractor shall participate in functional performance testing directed by the commissioning agent and shall correct deficiencies assigned to Contractor. Deferred seasonal tests shall be scheduled with Owner.

Frequently asked questions

What is the difference between TAB and commissioning?
Testing and balancing measures and adjusts airflow and water flow to design values. Commissioning is broader. It verifies that the systems meet the owner's requirements through documentation review and functional tests. Both produce reports, and they are often performed by different parties, so the scope should say which party owns each report.
Does the HVAC contractor do the balancing?
Sometimes, but on many projects an independent agency does it. The scope has to name the party. Davinci performs startup and checkout of the equipment it installs, while third-party TAB and owner commissioning are assigned separately and should be confirmed by the owner or general contractor.
What is a functional performance test?
It is a documented test that operates a system through its sequence of operation and records the result. Examples include switching between occupied and unoccupied modes, driving an economizer through its range or simulating a sensor failure. It needs a written sequence to measure against, which is why a vague sequence of operation becomes a commissioning problem later.
Why would testing be deferred to another season?
Because some conditions cannot be created during construction. A building finished in a mild month may not show peak cooling or winter heating behavior. The scope should list which tests are deferred, who attends and how results are recorded. Without that, deferred items are simply forgotten once the building is occupied.
Who pays when balancing has to be repeated?
The scope should say. If the system was not ready, such as closed dampers or unfinished controls, repeat visits are usually the responsibility of the party who declared readiness. Write the rule in advance and require a ready-for-balancing notice. It gives the agency a documented starting point and keeps repeat trips from becoming a dispute.

Performed by our own crew. No subcontractors.

The mechanical, refrigeration and controls work on our projects is done by our own UA Local 250 workforce. The people who price the job are the people who set the equipment, pipe it, charge it and start it up, so one team answers for every task in the scope. Rented equipment such as a crane truck is coordinated by us.

How self-performed work works

Send us the scope or the drawings.

If you are pricing a project or reviewing a bid, send the plans, the spec section or the equipment list. We will tell you what we would clarify before pricing it. Davinci Mechanical is the commercial and union division of Scottish Tom's Heating & Air.