Hospital and clinic HVAC scope of work: what it must cover

What a scope for hospital and clinic HVAC work should contain: infection control risk assessment, HCAI, pressure relationships, after-hours work and shutdowns.

For facilities directors, clinic administrators, owner's representatives, GCs. 5 min read. Updated November 2026.

Short answer

A scope for healthcare HVAC work must go beyond equipment. It should include an infection control risk assessment, state whether HCAI review applies to a licensed facility, define the required pressure relationships between spaces, plan after-hours work and shutdowns with clinical staff, and require testing and documentation before spaces return to service. This page describes what the scope should contain, not past projects.

Key points
  • In healthcare, the air is part of the patient environment. HVAC work is not a back-of-house activity.
  • An infection control risk assessment (ICRA) usually has to be done before work begins, and the scope should say who owns it and who signs off.
  • Licensed hospitals and some other facilities fall under HCAI review. Medical office clinics may not. Confirm which applies before pricing.
  • Pressure relationships between rooms must be stated, tested and recorded. Do not leave them to assumption.
  • Shutdowns of critical systems need a plan with temporary measures and a defined return-to-service test.

Why healthcare HVAC scopes read differently

A rooftop unit replacement at a retail center is an equipment project. The same unit serving a procedure room or an outpatient surgery suite is a patient-safety project. The mechanical work may be nearly identical. The scope around it is not.

This page describes what a healthcare HVAC scope should contain. It is a planning guide for owners, administrators and GCs. It is not a claim of healthcare project history, and the requirements that apply to a given building depend on its license type, its design and the local authority. Davinci is a commercial contractor whose mechanical, refrigeration and controls work is performed by our own UA Local 250 crew; if you are preparing a healthcare package, we will review it with you, and we will say plainly what falls outside our work.

First, what kind of facility is it?

The requirements stack up differently depending on the building type. Establish this before drafting anything.

Facility typeOversight to confirmScope implications
Licensed general acute care hospitalHCAI (the state healthcare facilities construction authority) review and inspection is likely to applyPermitting runs through that process; inspector of record, testing and observation requirements are part of the scope
Skilled nursing and some licensed clinicsHCAI or the local building department, depending on licenseConfirm which agency before the bid is released
Outpatient medical office or private clinicTypically local building departmentInfection control still applies even when HCAI does not
Dental, urgent care, imaging, dialysis, surgical centerMixed; depends on licensure and servicesAsk the owner for the licensing basis in writing
Veterinary clinicLocal building department and state rules for veterinary premisesOdor, animal comfort and surgery suite air need separate attention

If the answer is unclear, the scope should say so and require a determination from the owner or their design professional before construction starts. Requirements change, so confirm current rules with the relevant agency.

Infection control risk assessment

An ICRA is a structured review of how construction could affect patients, staff and visitors, usually done by the facility's infection prevention team with the project team. The result is a set of required precautions that become part of the contract.

  • Dust control: sealed barriers, negative air machines at the work area, sticky mats and protocols for ceiling tile removal.
  • Pathways: how workers, materials and debris move through occupied areas.
  • Duct and equipment handling: covering open ducts, wiping equipment before it enters, and protecting filters.
  • Water and Legionella considerations when cooling towers, domestic hot water or drains are disturbed.
  • Daily cleaning, inspection logs and the person with authority to stop work.
  • Final cleaning and clearance before spaces return to service.

The scope should state who prepares the ICRA, who implements barriers, who inspects them and what the stop-work trigger is. It should also say how the contractor's crew is briefed. Workers who have not been told the rules will break them without meaning to.

Pressure relationships and air quality

Healthcare spaces are designed with intended airflow direction: some rooms are kept positive so cleaner air flows out, others negative so contaminants stay in. Operating rooms, sterile processing, isolation rooms, soiled utility areas and waiting rooms each follow their own logic. HVAC work that changes airflow, even slightly, can disturb it.

  • List the affected rooms and their required pressure relationship from the design documents. Do not infer it from the name of the room.
  • Name the air change rates, filtration level and humidity control that the original design required, and require the replacement to meet them.
  • Require pressure and airflow measurements before and after, with the results recorded.
  • Identify who performs the independent testing and balancing. Davinci can take readings on its own installed equipment, but a third-party test-and-balance agency should be named when the project requires one. See testing, balancing and commissioning.
  • Keep spare filters, belts and critical parts policy defined for systems that cannot go down.

After-hours work and shutdown coordination

Many healthcare HVAC jobs cannot be done during clinic hours. The scope should state the work hours in clear terms, with premium-time or off-shift wages handled according to the contract and prevailing wage rules where they apply, without leaving the issue to be argued later.

  1. Identify each system shutdown, the spaces affected, the duration and the clinical contact who approves it.
  2. Define the temporary measures: portable cooling, rerouted air, relocated procedures or closed rooms.
  3. Schedule shutdowns in a written sequence with notice periods the facility can meet.
  4. Require a pre-shutdown walkthrough and a return-to-service test with a named witness.
  5. Provide an emergency recovery plan if the equipment cannot be restored on schedule.
  6. Record each event in the project log and the equipment asset record in the DaVinci Portal.

Coordinate roof and crane work with the facility's emergency egress, helipad or ambulance routes where applicable. The equipment removal, crane and rigging scope covers the lift planning side.

Power, controls and what belongs to other trades

Essential electrical systems, emergency power connections and fire alarm integration are not casual details in a healthcare facility. The scope should name the licensed party for each of these, and the owner or GC should confirm who is responsible. Davinci does not perform primary electrical service, feeder or panel work.

  • Which loads are on emergency power, and how the replacement equipment connects.
  • Fire and smoke damper coordination, with testing by the party that holds the responsibility.
  • Controls points for monitoring, alarms and trending, and who receives notifications after hours.
  • Equipment sound limits near patient rooms and consultation spaces.

Sample scope language and closeout documentation

Sample scope language

Contractor shall perform the work in accordance with the infection control risk assessment prepared by Owner and shall furnish and maintain the barriers and precautions it requires. Contractor shall perform work that affects occupied clinical areas during the hours stated in the work schedule and shall not interrupt ventilation to any space without written approval from Owner's designated clinical representative. Contractor shall measure and record airflow and pressure relationships in affected spaces before and after the work and shall report any deviation from design values to Owner.

Closeout in healthcare should include test results, filter specifications, sequence descriptions, maintenance procedures and an equipment record for every unit. A preventive maintenance program defined at handoff keeps the pressure relationships stable over time.

Frequently asked questions

Does a medical clinic HVAC project need HCAI review?
It depends on the license and the type of facility. HCAI oversees construction at licensed hospitals and certain other licensed healthcare buildings. Many outpatient clinics fall under the local building department instead. The owner or design professional should document which agency applies before the scope is finalized.
What is an infection control risk assessment?
A written review of how construction activity could affect patients and staff, producing required precautions such as barriers, negative air, cleaning routines and pathways. In many healthcare settings, it must be completed and approved before work begins, and it becomes part of the contractor's obligations.
Can HVAC work be done while patients are in the building?
Sometimes, with the right precautions and approved sequencing. Work in or above occupied clinical areas is usually restricted, and critical spaces may require after-hours or phased work. The scope should state exactly which areas allow daytime work and which do not.
Who verifies pressure relationships after the work?
The scope should name the verifying party. Often it is an independent test-and-balance agency, sometimes with the facility's engineering staff or commissioning agent witnessing. The mechanical contractor provides access, adjusts equipment and takes readings, but the verification party should be stated.
Do you claim healthcare project experience here?
No. This page describes what a good healthcare HVAC scope should contain. Davinci is a commercial and union contractor; if your project involves healthcare spaces, we can review the scope and tell you honestly which parts we can perform and which belong to other licensed parties.

Performed by our own crew. No subcontractors.

The mechanical, refrigeration and controls work on our projects is done by our own UA Local 250 workforce. The people who price the job are the people who set the equipment, pipe it, charge it and start it up, so one team answers for every task in the scope. Rented equipment such as a crane truck is coordinated by us.

How self-performed work works

Send us the scope or the drawings.

If you are pricing a project or reviewing a bid, send the plans, the spec section or the equipment list. We will tell you what we would clarify before pricing it. Davinci Mechanical is the commercial and union division of Scottish Tom's Heating & Air.