HVAC scope clarifications and exclusions checklist

More than 30 pre-bid clarification questions for commercial HVAC work, grouped by topic, plus the exclusions that most often turn into disputes.

For estimators, facility managers, GCs, procurement staff. 4 min read. Updated November 2026.

Short answer

Before pricing a commercial HVAC job, ask about access and hours, utilities, permits and fees, hazardous materials, roof and structure, electrical demarcation, controls, disposal, warranty start, commissioning and closeout. The answers fix the assumptions every bidder would otherwise make privately. Unanswered questions and unlisted exclusions are the most common source of later disputes and added cost.

Key points
  • Submit clarification questions in writing before the deadline and expect answers as addenda to all bidders.
  • Group questions by topic so the owner or GC can route each one to the right person.
  • If a question cannot be answered before bid day, state your assumption in the bid so it can be compared.
  • Exclusions that bite are usually about access, electrical, roofs, hazardous materials and closeout.
  • A short, honest list of exclusions is a sign of a careful bid, not an evasive one.

How to use this list

This is a working list, not a form to submit in full. Pick the questions the documents do not already answer, send them in writing, and keep the replies with the bid file. Owners and GCs can use the same list in reverse: if you cannot answer a question, bidders will assume an answer for you.

The list assumes you already have a draft scope. If you are still building one, start with how to write a commercial HVAC scope of work and come back here to pressure-test it.

Access, utilities, permits and fees

Access and working hours

  • What are the permitted working hours, and are nights or weekends required for any shutdown?
  • Is there a building badge, background check or escort requirement for the crew?
  • Where can vehicles park and where can material be staged?
  • Is roof access by fixed ladder, hatch or interior stair, and is fall protection already installed?
  • Are there blackout dates such as inventory, testing weeks, holidays or tenant events?

Utilities

  • Who arranges and pays for temporary power, water and gas shutdowns?
  • How much notice does the building need for an outage, and who communicates it to tenants?
  • Is there a utility-company step such as a gas meter change that sits outside the contractor schedule?

Permits and fees

  • Who pulls the mechanical permit, and who pays plan check, permit and inspection fees?
  • Is a separate electrical or structural permit needed, and who holds it?
  • Are there agency requirements such as DSA review for K-12 public schools or HCAI review for licensed healthcare facilities?
  • Confirm current energy-code documentation requirements for the replacement, including any acceptance testing.

Hazardous materials, roof and structure

  • Has the building been surveyed for asbestos, lead paint or other regulated materials, and is the report available?
  • Who handles abatement if suspect material is found, and how is the schedule affected?
  • Is refrigerant recovery from existing equipment included, and is the refrigerant type known?
  • What is the roof type and age, and who holds the roof warranty?
  • Who must be present or consulted when penetrations or curb work touch the roof membrane?
  • Has anyone confirmed that the structure can carry the new equipment weight, and who performs that review?
  • Is the existing curb reused, adapted or replaced, and who is responsible for the adapter?
  • Is crane access available, and who pays for street or lot closure if required?

For the crane and rigging side of these questions, see the equipment removal, crane and rigging scope.

Electrical demarcation and controls

Electrical and controls are the two areas where responsibilities blur fastest. A short table makes the demarcation questions concrete.

Electrical and controls clarification points
TopicQuestion to askWhy it matters
DisconnectWho furnishes and installs the unit disconnect?Often assumed by both parties or neither
Power to the equipmentWho runs the feeder and where does mechanical work begin?Primary electrical is a separate licensed trade; confirm the responsible party
CapacityHas the panel or service been checked for the new load?New equipment can draw differently than the old
Control wiringWho runs low-voltage wiring between equipment and thermostats or controllers?Typically mechanical or controls, but must be stated
Building automationIs a tie-in required, and what protocol and vendor are involved?Network access and passwords are owner-side
ProgrammingWho programs schedules and setpoints, and who approves them?Affects startup and closeout
Existing controlsAre existing thermostats or sensors reused?Reused devices may not match new equipment

Davinci's controls work is performed by its own crew. Electrical service, feeder and panel work is not part of that, so the scope should name the licensed party responsible and the owner or GC should confirm it. See building automation controls upgrade scope for more.

Disposal, warranty, commissioning and closeout

  • Who hauls and disposes of removed equipment, and does the owner want to keep anything?
  • Who handles refrigerant, oil and other regulated disposal documentation?
  • When does the equipment warranty start: at startup, at substantial completion or at owner acceptance?
  • Who is responsible for the labor portion of warranty repairs, and for how long, according to the bid documents?
  • Is third-party commissioning or testing and balancing required, and who hires that agency?
  • What documents are required at closeout: as-builts, startup reports, O&M manuals, test results?
  • Is owner training required, and for how many people or sessions?
  • How is the punch list generated, and who signs it off?
  • Is retention or final payment tied to documentation delivery?

Testing, balancing and commissioning questions go deeper in the sibling page on testing, balancing and commissioning scope.

The exclusions that bite

Exclusions are not a trick. They are a map of where the contractor stops and someone else starts. These are the ones that most often surprise owners.

Common exclusionWhat it can mean in practiceBetter wording
Structural workCurb framing, steel supports or roof reinforcement are not includedStructural by others; contractor coordinates with engineer of record
Primary electricalFeeders, panels and service upgrades are not includedElectrical by licensed party named by Owner or GC
Roof repairFlashing and membrane repairs beyond the curb footprint are not includedRoofing by others; contractor protects roof within the work area
AbatementAny asbestos or lead handling stops the jobAbatement by others; schedule impact addressed by change order
Concealed conditionsPipe, duct or wiring found behind finishes may add costNotice given on discovery; changes documented before proceeding
Finish repairsCeiling, paint and wall patching are not includedFinish work by others unless listed
After-hours premiumsNights and weekends are not in the base bidState hours assumed in the base bid
Closeout documentsTraining and as-builts are not pricedList required documents in the scope

Exclusions often become change orders when something is found. The related page on what triggers HVAC change orders shows how a tight scope reduces that.

Frequently asked questions

When are pre-bid clarification questions due?
The deadline is set in the bid documents, usually several days before bids are due so the owner or GC can issue an addendum. If no deadline is stated, ask as early as possible, since answers that arrive after bid day cannot be priced fairly across bidders.
What if my question is not answered before bids are due?
State your assumption clearly in the bid as a qualification, so the owner can compare it with other bids. An unstated assumption is invisible, and it often explains why one bid looks lower than the rest.
Should questions be sent to all bidders?
The answers should be. Good practice is for the owner or GC to issue every question and answer as an addendum to all bidders at the same time, so no one holds private information.
How many exclusions are too many?
There is no fixed number. A long list is fine if each item is specific and names who handles it. A short list of vague phrases like unforeseen conditions is worse, because it leaves the owner without a clear picture of what is included.
Who decides whether abatement or structural work is needed?
Owners typically rely on a qualified surveyor for hazardous materials and a structural engineer for load questions. An HVAC contractor can flag concerns and coordinate, but the owner or GC should confirm the responsible licensed party for those items.

Performed by our own crew. No subcontractors.

The mechanical, refrigeration and controls work on our projects is done by our own UA Local 250 workforce. The people who price the job are the people who set the equipment, pipe it, charge it and start it up, so one team answers for every task in the scope. Rented equipment such as a crane truck is coordinated by us.

How self-performed work works

Send us the scope or the drawings.

If you are pricing a project or reviewing a bid, send the plans, the spec section or the equipment list. We will tell you what we would clarify before pricing it. Davinci Mechanical is the commercial and union division of Scottish Tom's Heating & Air.